Construction
I-55 South of I-80 to South of Weber Rd — Bridge Preservation, Phase III Project
I-55, I-80 to Weber Rd. · 2021–Ongoing
- Client
- GSG Consultants, Inc.
- Owner
- Illinois Department of Transportation (IDOT)
- Location
- I-55, I-80 to Weber Rd.
- Year
- 2021–Ongoing
Project Overview
Description
Phase III construction engineering for bridge preservation along I-55 from south of I-80 to south of Weber Road.
HBM's Scope
Scope of Work
- Construction inspection
- Quality assurance
- Bridge preservation oversight
- HBM, in collaboration with GSG, provides construction inspection services
- Bridge deck enhancements: latex concrete overlay; bridge joint replacement/repairs; bridge deck grooving for skid resistance
- Approach slab and pavement upgrades; bridge deck scarification; HMA shoulder reconstruction (per MOT plan); longitudinal joint removal and pavement patching; Stone Matrix Asphalt (SMA) Mix 'F' for approach slab overlay and butt joint; full-depth patching into asphalt and concrete bases
- Construction inspection duties: supervision of workers, materials inspection per IDOT specifications, reporting to the Resident Engineer, daily records with field measurements and visual inspections, routine site inspections, and contractor coordination
Services Provided
Phase III Construction Engineering
Primary Discipline
Construction Engineering
Categories