COMED Bridge #8 Demolition Procedure — Chicago, IL

Project Overview

Description

Demolition procedure development for ComEd Bridge #8.

HBM's Scope

Scope of Work

  • Demolition procedure
  • Utility protection
  • Site safety analysis
  • Demolition plan for COMED Bridge #8 over S Commercial Avenue in Chicago; HBM in collaboration with Omega III
  • Bridge data: length 109'-11"; width 71'-11"; 2 spans; skew 50 degrees; 10 built-up girders; slab thickness 9.5 inches
  • Demolition slated for a 7-day duration; Omega ensuring on-site safety; decontamination for steel assumed to have lead paint
  • Equipment: 87K excavator, LTM 1130.51 crane, 40K loader, skid steer
  • Structural Analysis: MDX software for Load Factor analysis; models considered as-built conditions, section loss, and additional dead loads

Services Provided

Demolition Engineering

Primary Discipline

Research and Testing

Categories