Project Overview
Description
Demolition procedure development for ComEd Bridge #8.
HBM's Scope
Scope of Work
- Demolition procedure
- Utility protection
- Site safety analysis
- Demolition plan for COMED Bridge #8 over S Commercial Avenue in Chicago; HBM in collaboration with Omega III
- Bridge data: length 109'-11"; width 71'-11"; 2 spans; skew 50 degrees; 10 built-up girders; slab thickness 9.5 inches
- Demolition slated for a 7-day duration; Omega ensuring on-site safety; decontamination for steel assumed to have lead paint
- Equipment: 87K excavator, LTM 1130.51 crane, 40K loader, skid steer
- Structural Analysis: MDX software for Load Factor analysis; models considered as-built conditions, section loss, and additional dead loads